Gema OptiCenter OC09 - Filling the Optihopper; Coating; With Powder Recovery (Spray); Without Powder Recovery (Spray to Waste)

Gema OptiCenter OC09
112 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Rev. 00 02/21
60
Operation OptiCenter OC09
3. Select operating mode:
Coating
Cleaning operation mode
4. Set all other plant components to the correct operating mode (for
more information, see the relevant operating instructions)
If some plant components are not yet ready for operation, a
message will be displayed.
Filling the OptiHopper
Before coating, the OptiHopper must first be filled with powder. The level
is reached when the fluidized powder is 20 mm above the air suction
openings.
Manual filling is provided as standard. Optional fresh powder systems and
level sensors allow automatic filling.
The optional displacer can be used for processing small quantities of
powder (less than 11 kg). see chapter "Displacer**" on page 25.
Coating
With powder recovery (spray)
1.
Without powder recovery (spray to waste)
1. Reposition the recovery hose (connection on the back of the
OptiCenter housing)