4 Planning and installation – Installing the heating system
55
5. To transport the boiler with a crane, for example, the cover on the
blind side (2) if applicable, must be dismantled.
6. Fasten the crane hooks on the crane eyelets (3) according to the
instructions on the sticker (1).
7. Carefully lift the boiler.
I
NSTALLATION SITE 8. Transport the boiler to its installation site.
9. Place the boiler at the planned location while observing the mi-
nimum clearances.
See “4.1 Planning the heating system”, section “Required room
sizes and minimum spacing” in this chapter.
10.Align the boiler with plastic plates or flat steel strips (not included
in the scope of delivery) so that it is horizontal.
The boiler has been set up.
Figure 4/13 - Crane eyelets
3
1
2