5 Commissioning the system – Requirements
84
5 Commissioning the system
The heating system will initially be commissioned by specialists from
HDG Bavaria GmbH or an authorised HDG partner.
The commissioning includes an introduction to the operation and
maintenance of the heating system as well as performing measure-
ments on the system to determine exhaust emissions and firing per-
formance.
5.1 Requirements
The following conditions must be met before the system can be com-
missioned without faults:
S
WITCH OFF THE MAINS SUPPLY Is the circuit breaker of the mains supply to the heating system
switched off?
C
HECK THE MECHANICAL
STRUCTURE OF THE FEEDING
SYSTEM
Does the mechanical structure of the feeding system meet the
specifications of this operating manual?
C
HECK THE HYDRAULIC
CONNECTIONS
Do the hydraulic connections meet the specifications of this ope-
rating manual?
Has the safety equipment been installed to conform to the appli-
cable standards and guidelines?
C
HECK THE MECHANICAL
STRUCTURE OF THE HDG
C
OMPACT 25 - 80
Does the mechanical structure of the boiler meet the specifica-
tions of this operating manual?
Danger!
Material damage and injury due to incorrect commissioning
Commissioning the system requires comprehensive expertise. If
this commissioning is done by an untrained person, the heating
system could be damaged.
Only allow authorised specialists to perform the commissioning.