FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
3 Hardware Installation
Copyright © Huawei Technologies Co., Ltd.
27
2. Check the cabinet exterior for damage. If any damage is found, notify the carrier
immediately.
3. Check against the packing list that the equipment and fittings are correct and complete. If
some fittings are missing or do not comply with the packing list, record the information
and contact your local Huawei office immediately.
4. After checking that the cabinet is intact, remove the screw assemblies that secure the
cabinet to the pallet, as shown in Figure 3-1.
Set the screw assemblies aside for they will be used in installation steps.
Figure 3-1 Removing an ordinary cabinet
5. Remove the cabinet from the pallet and move the cabinet to the installation position.
To avoid personal injury, prevent the cabinet from falling over during transportation.
Step 5 Remove the pallet from the Converged Cabinet.
1. Remove the plastic bag and take out the fitting box, ramps, and sliders.

Table of Contents

Other manuals for Huawei FusionModule800

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei FusionModule800 and is the answer not in the manual?

Huawei FusionModule800 Specifications

General IconGeneral
BrandHuawei
ModelFusionModule800
CategoryStorage
LanguageEnglish

Related product manuals