NO TICE
A surge protection device must be congured for the upstream AC input of the
system. You need to congure and install the device by yourself.
The upstream AC input of the system must be congured with an AC circuit
breaker with a capacity of 40 A. The circuit breaker needs to be congured by
the customer. The D-type tripping circuit breaker cannot be used because it
cannot
eectively protect the product.
No leakage protection device is required for the upstream AC input. If a
leakage protection device is
congured, it is recommended that the leakage
current be greater than or equal to 100 mA x
n
, where
n
is the number of
power modules.
NO TE
In a single-node system, connect the other end of the AC input power cable to an AC PDC.
In a parallel system, connect the other end of the AC input power cable to the AC parallel
box.
Procedure
Step 1 Connect AC power cables to the terminal connectors.
Figure 8-61 Connecting cables to terminals
Step 2 Install the AC input power cable and secure the cable using cable clips.
iSitePower-M V100R002C00 User Manual
(MAP05A1, MAB05B1)
iSitePower-M V100R002C00 User Manual
(MAP05A1, MAB05B1) 8 Electrical Connection
Issue 01 (2022-07-15) Copyright © Huawei Technologies Co., Ltd. 131

Table of Contents

Related product manuals