CA UTION
Before cleaning the system, connecting cables, and checking the grounding
reliability, power o the system.
Table 10-1 Maintenance checklist
Check Item Check Method Maintenance
Interval
System
cleanliness
Check periodically that the heat sinks
are free from obstacles and dust.
Once every 6 to 12
months
System
running status
Check that the product is not
damaged or deformed.
Check that the product does not
generate abnormal sound when it is
operating.
Check that the parameters are
correctly set when the system is
running.
Once every 6
months
Electrical
connection
Check that cables are secured.
Check that the cables are intact,
especially that the parts touching
the metallic surface are not
scratched.
Check that the unused PV input
terminals, communications
terminals, and waterproof glands
are locked.
The rst inspection
is 6 months after
the initial
commissioning.
From then on, the
interval can be 6 to
12 months.
Grounding
reliability
Check that ground cables are securely
connected.
The rst inspection
is 6 months after
the initial
commissioning.
From then on, the
interval can be 6 to
12 months.
10.3 Troubleshooting
Alarm severities are dened as follows:
Major: The power system shuts down or some functions are abnormal due to
a fault.
Minor: Some components of the system are faulty but the system can still
operate.
iSitePower-M V100R002C00 User Manual
(MAP05A1, MAB05B1)
iSitePower-M V100R002C00 User Manual
(MAP05A1, MAB05B1) 10 System Maintenance
Issue 01 (2022-07-15) Copyright © Huawei Technologies Co., Ltd. 166

Table of Contents

Related product manuals