2. If grid power is unavailable, batteries supply power to loads. When the
battery depth of discharge (DOD) reaches the specied value, the genset is
started.
3. When the batteries are fully charged or grid power is available, the genset is
shut down.
4.4 Solar-Grid Hybrid Scenario
Figure 4-7 Solar-grid hybrid scenario network diagram (one product)
iSitePower-M V100R002C00 User Manual
(MAP05A1, MAB05B1)
iSitePower-M V100R002C00 User Manual
(MAP05A1, MAB05B1) 4 Application Scenarios
Issue 01 (2022-07-15) Copyright © Huawei Technologies Co., Ltd. 39