4.3 Genset-Grid Hybrid Scenario
Figure 4-5 Genset-grid hybrid scenario network diagram (one product)
Figure 4-6 Genset-grid hybrid scenario network diagram (multiple products
connected in parallel)
In the genset-grid hybrid scenario, the power system works circularly as follows.
The power source preference sequence is grid > battery > generator set (genset).
1. If grid power is available, grid power is supplied to loads and charges
batteries if batteries are not fully charged.