11 FAQs
11.1 Uneven Ground During the Installation
11.2 Tools for Preparing PV Cables
11.3 Special Cables
11.4 Removing Power Terminals
11.5 Power-On
11.6 SOC Changes
11.7 Checking Cable Connections when the Product Fails to Be Upgraded
11.8 WiFi QR Code Scanning
11.9 Querying the Battery Capacity in the Parallel System Scenario
11.10 Problem Handling
11.11 Resetting Password
11.1 Uneven Ground During the Installation
Use washers in the
tting bag to level the ground.
11.2 Tools for Preparing PV Cables
Use dedicated tools to prepare PV cables. Crimping tool model: PV-CZM-41100;
open-end wrench model: PV-MS-HZ
11.3 Special Cables
The battery power cable, battery power connector, and battery communications
cable are customized to be waterproof and moisture-proof. If they are lost or
damaged, contact your installer for replacement. Do not purchase or replace them
by yourself.
iSitePower-M V100R002C00 User Manual
(MAP05A1, MAB05B1)
iSitePower-M V100R002C00 User Manual
(MAP05A1, MAB05B1) 11 FAQs
Issue 01 (2022-07-15) Copyright © Huawei Technologies Co., Ltd. 177

Table of Contents

Related product manuals