Huawei iSitePower-M V100R002C00 - Optional Capacity Expansion Cable Installation

Huawei iSitePower-M V100R002C00
197 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Figure 8-84 Installing monitoring communications cables
----End
8.7 (Optional) Installing Cables in Capacity Expansion
Scenario
NO TICE
In capacity expansion scenarios, bottom cascading cables must be routed from
the rear of the product.
Cables outside the device must be routed through cable pipes.
8.7.1 Installing Ground Cables
D ANGER
Ensure that the ground cable is securely connected. Otherwise, electric shocks may
occur.
Procedure
Step 1 Install ground cables.
iSitePower-M V100R002C00 User Manual
(MAP05A1, MAB05B1)
iSitePower-M V100R002C00 User Manual
(MAP05A1, MAB05B1) 8 Electrical Connection
Issue 01 (2022-07-15) Copyright © Huawei Technologies Co., Ltd. 153