Figure 8-62 Installing an AC input power cable
----End
8.5.6 Installing Genset Control Signal Cables
NO TICE
For a genset that starts when the dry contact is open, connect the signal cable to
ports NO and COM. For a genset that starts when the dry contact is closed,
connect the signal cable to ports NC and COM.
Procedure
Step 1 Install genset control signal cables.
iSitePower-M V100R002C00 User Manual
(MAP05A1, MAB05B1)
iSitePower-M V100R002C00 User Manual
(MAP05A1, MAB05B1) 8 Electrical Connection
Issue 01 (2022-07-15) Copyright © Huawei Technologies Co., Ltd. 132