INSTALLATION MANUAL
FOR ELECTRICAL PARTS
2.4 Check List before Installation
READ “Safety Note” in this manual carefully in advance Check List.
First of all , the low speed operation should be completed since the work is performed according to WOS
engineering method. Therefore,
Check the following list before installation!
• Check 3 phase power applying status and the usage of NFB with appropriate capacity/Building.
• Install the locking device for the machine room to control the access of outsiders.
• Prevent water leakage from window or ventilation window of the machine room.
1) Check List for Machine Room
• Check the Hoist / Traction Machine
Check problem with oil (check the type of geared oil and whether the amount is changed)
Check if the project specification and the CAR number matches.
• Brake
Check the manual operation status of the brake part.
Check the spring adjustment value according to the capacity.
Check the status of foreign object and adjustment of the brake drum.
• Control Panel Installation
Check the space for work at the front side.
Check the vertical and horizontal level and fixing parts of Control Panel.
Select the location considering the installation of the cable duct.
• Governor
Check if the specification matches the governor installation status and speed.
During the work using WOS engineering method, make sure to install the governor.