Chapter 8. MetroCluster 121
8.7.1 MetroCluster host failure
In this scenario, N series N1 (Node 1) failed. CFO/MetroCluster takes over the services and
access to its disks, as shown in Figure 8-14. The fabric switches provide the connectivity for
the N series N2 and the hosts to continue to access data without interruption.
Figure 8-14 IBM System Storage N series failure
8.7.2 N series and expansion unit failure
Figure 8-15 shows the loss of one site, which results from failure of the controller and shelves
at the same time.
Figure 8-15 Controller and expansion unit failure
To continue access, a failover must be performed by the administrator by running the cfo -d
command. Data access is restored because DC1 mirror was in sync with DC1 primary.
Through connectivity that is provided by the fabric switches, all hosts again have access to