6.9 Sampling
6.9.1 Preparation
1. Select:
- [
^ ]
- [
< ]
- [
].
2. A new tab [
Sampling] opens.
3. In the field Sampling device, Use shuttle, select [
Yes].
4. Select [
Next].
5. When the screen changes to Connect the Shuttle now, when finished press next, select [
Open] in the field
Valve sampling.
6. Guide the hose (4) through the hole (5) of the sampling unit.
7. Connect the hose (4) to the nipple (3).
8. Select [
Close].
9. Remove the plug (2) from the knee (1).
10. Install the nipple (3) with the hose (4) into the hole in the knee (1).
11. Select [
Next].
12. Make sure the value in the field Current rack number is correct.
13. If necessary:
1. Select [
Change].
2. Type the correct value in the calculator.
3. Select [
ENTER].
14. Make sure the values in the fields Start position (bottle number) and End position (bottle number) are
correct.
15. If necessary:
1. Select [
Change].

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the LELY ASTRONAUT A3 and is the answer not in the manual?

LELY ASTRONAUT A3 Specifications

General IconGeneral
BrandLELY
ModelASTRONAUT A3
CategoryFarm Equipment
LanguageEnglish

Related product manuals