1. INSTALLATION
1.1 Installation Requirements
1.1.1 Delivery and installation work flow
Installation environment, floor strength
Installation
condition check
Operation check as far as the
machine stand-by condition
Machine power on
Delivery
Clamp removal
Main body setup
Installation of peripherals
Machine operation check
User guidance
Space around machine, delivery route
Power supply
The user’s acceptance of the limited items
for using the machine (See User Guidance
Items section for the limited items.)
Supply developer
Supply cleaning carrier
Set OPC belt
Supply silicon oil
Install power plug and cord
Leveling
Installing original stacker
Installing sub-tray
Installing toner cartridge
Setting copy paper
1 July 1994 Installation Requirements
1-1