EasyManua.ls Logo

SciCan Statim 5000 - 4. STATIM 5000 Calibration; Calibration Procedure 2: for Rev 2.x or 5.x Boards, Software R1.xx or R2.xx

SciCan Statim 5000
271 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Page 81
STAT
IM
2000/2000S Service Guide
96-106775 Rev 5.0
4. STAT
IM
5000 Calibration
STATIM 5000/5000S/5000 G4 Service Guide
STAT
IM
5000 Calibration
NOTE: Calibration Procedure 1: for Rev 3.x or 4.x Boards applies ONLY to STATim 2000 non S units.
Calibration Procedure 2:
for Rev 2.x or 5.x Boards, Software R1.xx or R2.xx
This calibration procedure is for STATIM 2000/5000 non S units (1995-2005) with revision 2.x or
5.x controller boards and revision 1.xx or 2.xx software.
Important:
• Incorrect or inaccurate calibration may cause unsuccessful sterilization of instruments.
• Always calibrate the thermocouples after a thermocouple replacement, thermocouple bend
or disconnect, controller board replacement or microprocessor / EEPROM replacement,
steam generator replacement or probe bracket replacement.
• Make sure that there is sufficient steam-process distilled water in the unit prior to starting
calibration.
• Do not place the digital reference thermometer in direct sunlight, on the armature or on any
other hot surfaces. This may cause improper values on the temperature readout.
• There are specific error messages (cycle faults) for these board/software types, which can
be found in the
Troubleshooting Cycle Faults
section.
• In calibration mode, no error messages are displayed.
Calibration Procedure
Calibration of these boards should be done in the following order:
1. Reference voltage verification / adjustment
2. Steam generator thermocouple calibration (automatic)
3. Chamber thermocouple calibration
4. Steam generator re-calibration (automatic)
Required equipment:
• Control box - 01-103141S
• Digital voltmeter
• Calibration cassette (appropriate to model)
• Potentiometer trimmer
• Calibration jumper
• Digital thermometer
Setting up the unit for calibration:
• Before starting calibration, turn the STAT
IM
OFF and remove the cover.
• Check that there is sufficient steam process distilled water in the reservoir, and that the
calibration cassette (6) is correctly engaged in the STAT
IM
.
• Install the thermocouple (7) into the cassette and attach the digital thermometer (8).
• Ensure that the thermocouple and digital thermometer have matched serial numbers.
• Install the calibration jumper (11) to controller board pins marked W1 (10).