Startup procedure for the DFE32B option as gateway
Project Planning with PROFINET
5.6.2 Starting up units with DC 24 V or AC 400 V
Step 1: Configure MOVITRAC
®
B
1. Start MOVITOOLS
®
MotionStudio and open a new project.
Specify a project name and assign USB11A programming interface according to se-
rial COM interface.
– When the USB11A programming interface is connected to the PC for the first
time, Windows hardware detection installs the required FTDI driver
– If USB11A is not recognized, check the assignment to the COM interface. The
matching COM port is marked by "USB".
2. Connect the PC to MOVITRAC
®
B via USB11A programming interface.
3. Perform a unit scan. To do so, select the unit using the mouse button and make a
right-mouse click to open the context menu. Then choose [Startup] / [Parameter tree]
from the menu.
4. Set the parameters for P881 SBus address in ascending order (1 ... 8) unequal to 0
Set P883 SBus timeout interval to 50 ... 200 ms
5. Set P100 setpoint source to "SBus1/fixed setpoint" and P101 control signal source
to "SBus1".
6. For simple control via fieldbus, the binary inputs can be set to "No Function" via pa-
rameters P601 ... P608.
7. Check the parameterization for the process data (P87x). The parameters for control
word and status word must be set. Set P876 PO data enable to "Yes".
8. Repeat steps 2 to 7 for the individual units connected to the SBus.
9. Activate Auto setup function via "AS" DIP switch of the DFx gateway. Set "AS" DIP
switch to 1. H1 LED flashes during the scan and goes out after successful comple-
tion.
10.Connect the PC to DFx gateway via USB11A programming interface.
11.Perform a unit scan. The DFx gateway and all units installed at the SBus must be
accessible now.
12.Select DFx gateway and open the context menu with a right mouse click. Choose [Di-
agnostics] / [Monitor Fieldbus Gateway DFx] from the menu. Go to the "Gateway
Configuration" tab page and check whether the "Auto setup" function has recognized
all units. If not, check
– the SBus installation
– Whether the terminating resistor is connected to the final unit
– The SBus addresses of the individual units