EasyManuals Logo

Siemens SIROTEC Engineering Manual

Siemens SIROTEC
530 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #247 background imageLoading...
Page #247 background image
EMC Installation Guideline
Engineering Information
SINAMICS Engineering Manual – November 2015
Ó Siemens AG
247/528
2.4.7.3 EMC-compliant cable routing on the plant side on cable racks and in cable ducts
1)
When single-wire cables (e.g. unshielded supply connection cables) are used in three-phase systems, the three
phase conductors (L1, L2, and L3) must be bundled as symmetrically as possible to minimize the magnetic leakage
fields. This is particularly important when several single-wire cables need to be routed in parallel for each phase of a
three-phase system due to high amperages. The illustration below uses an example of a three-phase system with
three single-wire cables per phase routed in parallel (with and without PE conductor).
a) Three parallel single-wire cables per phase with PE conductor
b) Three parallel single-wire cables per phase without PE conductor
If the preferred two-layer bundle arrangement illustrated above is not feasible for mechanical reasons with special
applications– for example, where trailing cables are used – then the cables must be bundled in one layer in a single
plane as illustrated in the diagram below.
a) Three parallel single-wire cables per phase with PE conductor in a single plane
b) Three parallel single-wire cables per phase without PE conductor in a single plane
2)
and
3)
: See following page for explanations

Table of Contents

Other manuals for Siemens SIROTEC

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SIROTEC and is the answer not in the manual?

Siemens SIROTEC Specifications

General IconGeneral
BrandSiemens
ModelSIROTEC
CategoryDC Drives
LanguageEnglish

Related product manuals