Figure 5-2 Incorrect installation
Ensure that the length of the dead space at the end of the process connection is smaller than
its diameter.
To ensure optimal cleaning of the process plant, install the process connection without
offset (flush-mounted on inside) in the plant.
You can find additional information in the EHEDG Guidelines No. 10 and No. 37.
5.3 Installation (level)
Mounting location
Verify that the mounting location meets the following conditions:
Accessible
Close to the measuring point
Vibration-free
Within the permitted ambient temperature values
Protect the pressure transmitter from:
Direct heat radiation
Rapid temperature fluctuations
Heavy contamination
Mechanical damage
Direct sunlight
Note
Select the
height of the mounting flange such that the pressure transmitter is always mounted
below the lowest fill height to be measured.
Requirement
You have compared the desired operating data with the data on the nameplate.
You have adhered to the information on the remote seal during its installation.
Installing/mounting
5.3 Installation (level)
SITRANS P320/P420 with 4 to 20 mA/HART
Operating Instructions, 11/2019, A5E44852162-AC 51

Table of Contents

Other manuals for Siemens SITRANS P

Related product manuals