12.4.3 Inserting the Cables
1. Remove the screws at the top of the sealing plate.
2. Remove the sealing plate.
3. Loosen the screws at the side of the sealing plate.
4. Remove the required number of rubber seals from the sealing plate. Make sure that the diameter of the rubber
seals corresponds to the diameter of the cables to be inserted. Use the additional rubber seals included in the
scope of delivery, if necessary.
5. Remove the sealing plugs from those rubber seals through which the cables are to be led.
6. Lead the cables through the rubber seals.
7. Insert the rubber seals in the sealing plate avoiding any distortion. This will ensure the tightness of the seal.
8. Tighten the screws at the side of the sealing plate.
9. Screw the sealing plate to the floor of the interface cabinet.