7 Commissioning User Manual
60
Zero-export (Partial):
ON: no power will be exported to the grid.
OFF: all inverter output power will be exported to the
grid.
Partial: set partial of the output power to export to the
grid.
According to the local regulations in Germany, please
set the export power to 70 % of the installation
capacity.
For example, with a total maximum installation capacity
of 4600 W (SH4K6), the export power should be set to
3220 W (i.e. 4600 * 70 %).
Partial
2/2
Zero-export
ON
OFF
Partial
1/2
Export Pwr[W] 04600
Export power range:
When the existing system is disabled, the range is from 0 to the rated power of
the hybrid inverter.
When the existing system is enabled,
− the lower limit is the rated power of the existing PV system.
− the upper limit is ([rated power of the hybrid inverter] + [rated power of
the existing PV system]).
− the value will synchronize with the settings for retrofitting an existing
system described in section 10.4.2 .
Reactive power regulation:
OFF:
The reactive power regulation function is disabled.
The power factor (PF) is limited to +1.000.
Reactive Power
PF
OFF
Q(U)
Q(P)
Qt
“PF” mode:
The inverter is capable of operating with fixed power
factor.
The PF ranges from 0.8 leading to 0.8 lagging.
Leading: the inverter is sourcing reactive power to the
grid.
Lagging: the inverter is sinking reactive power from the
grid.
PF Setting
PF + 1.000
+ : Laggingg & - : Leading
For the explanations of other modes, see “11 Appendix IV: Power Response”.
Battery usage enabled (Weekend):
Bat Usage Time
Weekday Usage
Weekend Usage
Weekend Usage
Disable
Enable
Start Time 1
End Time 1
00:00
24:00
Start Time 2
End Time 2
00:00
24:00
Press
ENT
Press
ENT
(Optional) For lead-acid batteries, you should manually set the battery type.