Section 4: Use the RPM to switch the SMU, CVU, and PMU 4200A-SCS Parameter Analyzer User's Manual
4-6 4200A-900-01 Rev. D/April 2020
Create a new project
To create a new project:
1. Choose Select.
Figure 32: Select highlighted
2. In the Library, select Projects.
3. Select New Project.
4. Select Create.
Figure 33: Select a New Project from the Project Library
5. Select Yes when prompted to replace the existing project.
6. Select Rename to assign a new title to the project.
7. Enter Diode Test.
8. Select Enter.