19. Install the two (2) alignment pins and install a new
center section gasket onto the housing (Fig. 74).
Figure 74
20. Install center section with valve plates onto trans-
mission housing (Fig. 75).
IMPORTANT: Make sure all parts are properly
aligned. Do not force center section into position on
the housing.
NOTE: When the center section is properly installed, the
cylinder block springs will hold the end center section
away from the housing approximately 1/8 in.
Figure 75
21. Install the six (6) screws that retain the center
section to the housing and torque evenly to 33 to 41 ft-lb
(Fig. 76).
22. Rotate the pump and motor shafts to make sure
t
ransmission is assembled correctly. When properly
assembled, a maximum torque of 3.5 ft-lb should be
required to turn either shaft.
23. Assemble the following components as described in
previous procedur
es:
Charge Check / High Pressure Relief Valves
Figure 76
Charge Relief Valve
Heat
Exchanger Bypass Valve
Filter Bypass Valve
Filter Bypass Reverse Flow Check Valve
Charge Pump
Reelmaster
®
5100-D Page 4 - 53 Transmission Repairs