D301087 0308 - BL20 CANopen 7-3
General Notes
7
The group combinations:
Group 1/Group 3 and Group 2/Group 3
must be routed in separate cable ducts with a minimum distance of
10 cm apart. This is equally valid for inside buildings as well as for
inside and outside of switchgear cabinets.
Cable Routing Outside Buildings
Outside of buildings, cables should be routed in closed (where
possible), cage-type cable ducts made of metal. The cable duct
joints must be electrically connected and the cable ducts must be
earthed.
Lightning Protection
The cables must be routed in double-grounded metal piping or in
reinforced concrete cable ducts.
Signal cables must be protected against overvoltage by varistors or
inert-gas filled overvoltage arrestors. Varistors and overvoltage
arrestors must be installed at the point where the cables enter the
building.
Transmission Cables
The slaves on the bus are connected to one another with fieldbus
lines that correspond to the DeviceNet specification (ODVA Spec.
Rel. V2.0).
Warning
Observe all valid guidelines concerning internal and external light-
ning protection and grounding specifications when routing cables
outside of buildings.