Oven installation is divided into 5 stages:
1) Preliminary and positioning procedures
2) Electrical connection / Gas connection
3) Plumbing: water supply
4) Plumbing: water drainage
5) Smoke exhaust outlet
2
3
5
1
4
Preliminary and positioning procedures
Installation site
Before positioning the appliance, check the measurements and the exact position of the electrical, plumbing
and smoke exhaust connections, in accordance with the figures provided in the enclosed "Technical Data"
booklet.
Caution!
Do not install the appliance near flammable materials.
If the appliance is positioned near walls, partitions, kitchen cabinets, decorative trim, etc., these items must be
made from non-flammable material.
If this is not the case, they must be coated with a non-flammable heat insulating material, and all fire prevention
regulations must be strictly observed.
33
Appliance installation
1. Positioning
2. Electrical connection
3. Water supply
4. Water drainage
5. Smoke exhaust outlet