Installation
February 2011 2-4 P/N 06-237041-001
2-3.6 Step Six: Install Batteries
Install standby batteries into bottom tier or Large Capacity Battery Cabinet.
2-3.7 Step Seven: Install Expansion Enclosures and/or Remote Modules (if applicable)
Install add-on cabinets and equipment: Expansion Enclosure(s), Remote Display Control
Modules, LED Annunciator Modules, additional Power Supply/PMU Assembl(ies),
additional Card Cages.
Dress and connect field wiring to applicable modules as shown on the approved system drawings
and as illustrated in this manual.
Make internal DC power and COM connections.
2-3.8 Step Eight: Auto-configuring the System
Auto-configure the system as directed in Section 3-1.1. Print out the list of SLC-based initiating
devices and addressable control and/or relay modules detected by these procedures and
compare this list to the approved set of SLC devices. Correct any inconsistencies and/or trouble
messages.
2-3.9 Step Nine: Uploading the Configuration File and Performing the Pre-Test
Upload the site-specific configuration file. After uploading the configuration file, the control unit will
restart in order to begin using the new settings. Note that the USB or RS232 cable should be
disconnected at this time.
Pre-test the system in accordance with the approved sequence of operation. Be sure that
extinguishing-system actuation devices are not connected to the extinguishing system during pre-
testing.
2-3.10 Step Ten: Performing Final System Test and Commissioning the System
Final test and commission the system in the presence of the owner and the authority having
jurisdiction. Be sure that extinguishing-system actuation devices are not connected to the
extinguishing system during final testing.
2-3.11 Step Eleven: Installing the Actuation Devices and Extinguishing System
Connect the actuation devices to the extinguishing system per the procedures in the applicable
suppression system installation manual.
2-3.12 Step Twelve: Performing Final Installation Procedures
Install the front door when testing is completed, all appropriate occupancy certificates have been
secured, the end user has been thoroughly trained in the system operation, and the system is armed
and ready for service. Lock the front door and give the key to the end user's designated personnel.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the UTC Fire and Security FenwalNET 8000-ML and is the answer not in the manual?

UTC Fire and Security FenwalNET 8000-ML Specifications

General IconGeneral
BrandUTC Fire and Security
ModelFenwalNET 8000-ML
CategoryControl Unit
LanguageEnglish