116 HB700 | CPU | PMC921xEx | en | 24-04
Deployment CPU iC921xM-FSoE
iC9200 Series
Commissioning > Notes on commissioning
WARNING
Safety function only ensured after validation
The planned safety function of the plant/machine is only ensured after
validation.
WARNING
Organizational or technical measures required for compensation of the CRC
checksum
T
ake technical or organisational measures to ensure that the correct project
for the application is started in the CPU by comparing the CRC checksum:
‘Comparison of the checksums’...page 123
After transferring a project to the CPU.
A valid but incorrect project for the application could be loaded.
After removing the SD card.
There could be a valid project in the internal memory but the incorrect
one for the application.
After inserting or changing the SD card.
There could be a valid project on the SD card but the incorrect one for
the application.
If you use a technical measure to check the CRC checksum, it must be
implemented in such a way that the check done by a third technical instance
outside the safety CPU.
WARNING
Safety and availability of the plant/machine
Ensure the safety and availability of your plant/machine by selecting the
appropriate watchdog time FSoE_WD_T
ime.
Select the watchdog time high enough so that the safety of your plant/
machine is still guaranteed with the highest possible availability
.
WARNING
Avoid danger caused by triggering the safety function too late
Ensure that the maximum permissible values TI
FSoEWD_MAX
and
T
O
FSoEWD_MAX
are not exceeded. ‘Maximum permitted watchdog
times’...page 134
WARNING
Debug operation
Switching to debug operation means leaving normal operation.
Make sure that your plant/machine does not pose any danger to people
during debug operation and that no damage can be caused.
NOTICE
Acclimatization before start-up
Make sure that commissioning only takes place after the CPU and the associ-
ated modules have acclimatized!