ABB ACQ580 - Multipump Maintenance and Monitoring

ABB ACQ580
422 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Parameters 267
76.105 IPC synchronization
checksum
Displays the calculated parameter checksum (CRC) of the
parameter groups selected with parameter 76.102 IPC
synchronization settings. If the value of this parameter is
same on all the drives, then the configuration is also
synchronized correctly.
77
77 Multipump
maintenance and
monitoring
Multipump maintenance and monitoring parameters.
77.10 PFC runtime
change
Enables the reset, or arbitrary setting, of 77.11 Pump 1
running time77.18 Pump 8 running time.
Done
Done The parameter automatically reverts back to this value. 0
Set any PFC run
time
Enables the setting of 77.11 Pump 1 running time77.18
Pump 8 running time to an arbitrary value.
1
Reset PFC1 run
time
Resets parameter 77.11 Pump 1 running time.2
Reset PFC2 run
time
Resets parameter 77.12 Pump 2 running time.3
Reset PFC3 run
time
Resets parameter 77.13 Pump 3 running time.4
Reset PFC4 run
time
Resets parameter 77.14 Pump 4 running time.4
Reset PFC5 run
time
Resets parameter 77.15 Pump 5 running time.6
Reset PFC6 run
time
Resets parameter 77.16 Pump 6 running time.7
Reset PFC7 run
time
Resets parameter 77.17 Pump 7 running time.8
Reset PFC8 run
time
Resets parameter 77.18 Pump 8 running time.9
77.11 Pump 1 running
time
Running time counter of pump 1. Can be set or reset by
parameter 77.10 Pump 1 running time.
0.00 h
0.00…
42949672.95 h
Time 1 = 1 h
77.12 Pump 2 running
time
See parameter 77.11 Pump 1 running time.0.00h
77.13 Pump 3 running
time
See parameter 77.11 Pump 1 running time.0.00h
No. Name/Value Description Def/FbEq16
Bit Name Value
0 AI parameters Parameter group 12 Standard AI.
1 Process PID set 1
parameters
Parameter group 40 Process PID set 1.
Parameters 19.11 Ext1/Ext2 selection, 20.06 Ext2 commands,
20.08 Ext2 in1 source, 22.18 Ext2 speed ref1 and 28.15 Ext2
frequency ref1.
2 IPC parameters Parameter group 76 Multipump configuration and 77
Multipump maintenance and monitoring.
3…15 Reserved