Mechanical installation
56
Checking the delivery
The drive delivery contains:
• drive cabinet line-up
• optional modules (if ordered) installed into the control rack at the factory
• winch for the supply and inverter module replacement (if ordered)
• installation stand (delivered in a separate pallet)
• appropriate drive and optional module manuals
• delivery documents.
Check that there are no signs of damage. Before attempting installation and
operation, check the information on the type designation label of the drive to verify
that the delivery is of the correct type. See Type designation key on page 50.
Moving the unit
Moving the unit by crane
Use the steel lifting bars attached to the top of the cabinet. Insert
the lifting ropes or slings into the holes of the lifting bars.
The lifting bars can be removed (not mandatory) once the cabinet
is in its final position. If the lifting bars are removed, the bolts
must be refastened to retain the degree of protection of the
cabinet.