Mechanical installation
64
Connecting the liquid pipes
1. Ensure the Axilock connectors are slid on pipe ends. See section Preparing the
liquid pipe connections on page 63.
2. Position the liquid pipe ends against each other.
3. Centre the Axilock connector onto the pipe ends.
4. Tighten the connector bolts to a torque shown on the label attached to the
connector.
Connecting the PE busbars
Connect the PE busbars as shown below.
Parallel
misalignment:
max 3 mm (0.2”)
Angular error:
max 2° in any
direction
Axial gap: 5 to
15 mm (0.2” to
0.6”)
2
3
Tightening torque: 35–40 N·m (25–30 lbf·ft)
Strength class: 8.8
Spring washer
Plain washer
Plain washer
M10