Iteration of the standard test procedure as per IEC 61000-4-12 
The ring wave has to be applied 
synchronized to the voltage phase at 
the respective angle and the peak 
value of the ac. voltage wave (positive 
and negative). 
The ring wave has to be applied 
between lines and between line(s) and 
earth. When testing line to earth the 
test voltage has to be applied 
successively between each of the lines 
and earth. 
The test voltage has to be increased 
by steps from the lowest test level up 
to the test level specified in the product 