Installation
40 EN 03|2022
Fig. 4
5.2 Installation
The control can be installed above or below the water level.
For installation below the water level, observe the following points:
If the control is installed between 1 m and 3 m below the
water level, a spring loaded SPECK non-return valve must be
installed (a).
Installation at 3 m to 6 m below the water level should be
avoided. Deeper than 6 m is not permitted.
Either a spring loaded SPECK non-return valve (article no.
240.9102.063) or an assembly bow to the water level must
be installed in the sewage line (b).
control (wear
SELV
230 V
315 mAT
4 AT
WG27.50.128-2-P
Low voltage