BADU OmniTronic - Commissioning and Decommissioning; Commissioning Procedures; Shut-off Valves

BADU OmniTronic
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Commissioning/Decommissioning
03|2022 EN 49
6 Commissioning/Decommissioning
6.1 Commissioning
power supply.
6.1.1 Switching on
Do not switch on the device until the drive box is fully connected
to the electronics.
Î The screws of the lid must be firmly tightened so that the
correct distance from the keyboard is kept.
Î Fit the lid carefully and in the correct position so that the
keyboard is not damaged.
6.2 Functional test
6.2.1 Test cycle
Once the supply voltage has been applied and the control has
been turned on with the illuminated rocker switch, the device runs
a test cycle. This ends in the position “Filter”. Then the device is
ready for operation.
6.2.2 Shut-off valves
The integrated shut-off valves in the control connection lines must
be opened completely.