Safety Manual / Explosion Protection Manual 11 Plan for the Control of the Connection
56926BA26, Rev. 06, 04/2019
11 Plan for the Control of the Con-
nection
If you answer any of these questions with "No", you must make a note of the
measures you have taken to remedy this deficiency in the last column. Before
you take the detector into operation, make sure to verify the correctness of the
measures with your explosion protection officer again.
Date:………………..
Name:………………………………..
Examination in the connection compartment
Is the interior (connection compartment) in good
condition?
Is the interior dry, clean and free of debris?
Are the clamped conductors firmly seated?
Are the terminals in good condition?
Is the interior free from corrosion?
Is the insulation free of damage or creepage
paths?
Is the mechanical attachment of the components
intact?
Is the detector properly installed according to EN
60079-14?
For fine wired strands: Are all the wires from the
terminals covered and clamped?
The connection of superfine stranded lead of
class 6, according to IEC 60228, is not permitted.
Is the equipotential bonding properly con-
nected?
Is the screen properly isolated electrically (e.g.
with shrink tubing)?