2. Commissioning
2-20
Festo P.BE-CPX-PNIO-E N en 1407c English
Note
There are different configuration programs available in
combination with a Siemens PLC
Observe the corresponding procedure for your configura-
tion program.
Caution
Danger of mal functions, damage or injuries to people
A valve terminal will be put into operation even if it is in-
correctly configured. However, only the modules whi ch
have been correctly configured for type and position will
be activated.
Before commission ing, make sure that the connected com-
ponents (e.g. actuators) do not perform any unexpected or
uncontrollable movements.
If necessary, d isconnect the load power supply and com-
pressed air supply.
See also section 2.11: Check list for commissioning the
CPX terminal.