4. UNPACKING
Care must be taken when unpacking and installing the relays so that none of the parts are
damaged and additional components are not accidentally left in the packing or lost.
Note: With the lower access cover open, the red tab of the battery isolation
strip will be seen protruding from the positive side of the battery
compartment. Do not remove this strip because it prevents battery
drain during transportation and storage and will be removed as part of
the commissioning tests.
Relays must only be handled by skilled persons.
The site should be well lit to facilitate inspection, clean, dry and reasonably free from dust
and excessive vibration. This particularly applies to installations which are being carried out
at the same time as construction work.