8-138 Section 8-6 - Mechanical Parts- Replacement Procedures
D
IRECTION 5771498-100, REVISION 6 VENUE™ SERVICE MANUAL
PRELIMINARY
8-7-5-5 MPB TO BE PWR Cable Installation Procedure
1.) Connect the cable using the two plastic cable clips
2.) Connect the two lower cable connectors by sliding them downwards
3.) Install the MPB module.
4) Install the MPB Front Metal Door.
5.) Refit the following covers: MPB Door Cover, Left and Right Side eTower Covers, Lower Front
eTower Cover, and RS Probe cover
6.) Install all accessories.
7.) Turn ON power to the system.
MPB Module Installation Procedure
MPB Front Metal Door Installation Procedure
MPB Door Cover Installation Procedure
Left Side eTower Cover Installation Procedure
Right Side eTower Cover Installation Procedure
Lower Front eTower Cover Installation Procedure
RS Probe Cover Installation Procedure
Accessories - Replacement Procedures
Perform the checks listed in MPB to BIB Control Cable Replacement Procedure on page 8-218