Reinstall the middle cover and torque the fourteen M4 ×12 mm Torx screws to 10.4 in-lb.
Reinstall the front cover and torque the two M4 ×12 mm Torx screws to 10.4 in-lb.
WARNING! Double check that covers are properly assembled and fastened to ensure high voltage is not
accessible.
Commissioning, Device Replacement, and Maintenance
This section walks you through the steps to commission or perform maintenance on a GM Energy V2H Bundle.
Before beginning this process, please ensure you have completed all necessary steps documented above in this manual.
Visit https://gmenergy.gm.com/for-home/installation-support to download the most recent PowerShift Install
commissioning app.
For the intent and purpose of this section the following equipment will be referenced as the following below and in the
PowerShift Install commissioning app:
• GM Energy PowerShift Charger: EVSE
• GM Energy Inverter: BDI
• GM Energy Home Hub: MID
• GM Energy Dark Start Battery: DSB
Pre-Commissioning Systems Check
Power on all systems
• Verify the breaker feeding the MID is closed and valid grid voltage is available to energize the MID. LED on the BDI
and EVSE should be on.
o Energize all circuits within the MID including the BDI and EVSE.
• For installations including the EVSE, ensure the Charger connector is in the holster and not plugged into the vehicle.