GM Energy V2H Bundle Installation Manual 75
Commissioning Closeout
After commissioning is successful (confirmed cloud connections, hardware statuses, settings, and readings, and overall
functionality), leave the system in a state that is compliant with all local requirements imposed by the utility, AHJ, or other
regulatory body. This may require locking out or flipping breakers to the equipment. The Installer should communicate with the
customer of when the system is approved to operate.
Job Closeout
Remove and discard the protective film from the Charger.
For installations that include the Charger and V2H Bundle, it is recommended to complete the System & Voltage Checks Form,
available in