Figure 5-5 Marking the mounting holes for battery modules
Step 4 Drill holes and install expansion bolts.
D ANGER
When drilling holes, avoid the water pipes and power cables buried in the wall.
Figure 5-6 Installing expansion bolts
NO TE
Use the M6x60 expansion bolts delivered with the product to secure the mounting base. If
the length or quantity of the M6x60 expansion bolts cannot meet the installation
requirements, prepare M6 stainless steel expansion bolts by yourself. The expansion bolts
delivered with the product are used for solid brick walls and concrete grounds. If other
types of walls and grounds are used, ensure that the load bearing capacity requirements
(the weight of one battery module is 50 kg) are met and appropriate bolts are selected.
iSitePower-M V100R002C00 User Manual
(MAP05A1, MAB05B1)
iSitePower-M V100R002C00 User Manual
(MAP05A1, MAB05B1) 5 System Installation
Issue 01 (2022-07-15) Copyright © Huawei Technologies Co., Ltd. 51