8. From the Configure DRM Network qfe0 Port Sub-menu, select "Return to the
main menu".
Note: The user must now reboot the DRM AW before the changes to the DRM
Network configuration can take effect.
9. Perform Administrative Workstation Maintenance Procedure 4.1” Halt the
Administrative Module (AM) Emulator”.
10. Switch to the UNIX console of the AW by holding down the Ctrl key and
pressing Enter (not Return) on the MCC.
11. From the Administrative Workstation Main Menu, select "Boot the Workstation."
Answer yes to the confirmation. If you select a task by mistake, answer no to
the confirmation.
Response:
You have chosen to boot the workstation. If the Emulator is running,
it must be halted before continuing. Refer to the Main Menu item of
Halt the Emulator.
Do you want to continue? (yes/no) yes
12. Wait for the boot sequence to complete and then switch back to the MCC view by
holding down the Ctrl Key and pressing Enter (not Return).
13. STOP. YOU HAVE COMPLETED THIS PROCEDURE
235-200-150
May 2003
APPENDIX 5
5ESS Switch DRM Administrative Workstation
NETRA
t 1120
to
NETRA
20 WITH SOLARIS 8 OS CONVERSION PROCESS
GUIDELINES
Issue 3.00 Page A5-11