Comet Executive Gas Installation
2-15
Final Protective Wrapper Removal
1. Carefully remove any remaining plastic
protective coverings from the unit. Do
not remove the guide tapes (Figure 2-3).
2. Remove any wooden wedges used to
hold the ironing cylinder in place during
shipment, and save the wedges for main-
tenance and repair work.
3. The brown paper covering the ironing
cylinder will be removed after machine
phasing is veried, and safety and control
functions have been checked.
2.3 Pre-Operational
Checkout
NOTE: For more information
about the controls mentioned in
the following procedures, refer
to Operating Controls on page
3-4.
Before the unit can be placed into full
operation, perform the following procedures:
• Security of Hardware
• Exhaust Blower Motor Rotation
Checkout
• Safety Device and Control Function
Checkout
• Ironing Cylinder Paper Removal
• Gas Connection Checkout
• Checkout Completion
• Cleaning the Unit
WARNING
Do not put the unit into
service until all controls
are functioning properly.
Failure to do so may result in
serious injury to operators or
maintenance personnel.