Hardware Installation and Setup
3-2
Part 1120130
E 2011 Nordson Corporation
Installation Tasks
The installation sequence is as follows:
1. Verify that the required environmental conditions and utilities exist.
2. Unpack and inspect the melter.
3. Configuring the Electrical Service.
4. Connecting Hoses and Applicators.
5. Setting Up Inputs/Outputs.
6. Setting Up Gear-to-Line Operations.
7. Installing Optional Equipment.
8. Connect an applicator driver, pattern controller, or timer.
9. Flush the melter.
Experience of Installation Personnel
The instructions provided in this section are intended to be used by
personnel who have experience in the following subjects:
S Hot melt application processes
S Industrial power and control wiring
S Industrial mechanical installation practices
S Basic process control and instrumentation
Installation Requirements
Before installing the melter, ensure that the desired installation location
provides the required clearances, environmental conditions, and utilities.
Clearances
Figures 3‐1 through 3‐3 illustrate the minimum clearances that are required
between the melter and surrounding objects.

Table of Contents

Related product manuals