9 Tabular overview of the program procedures Charge
70 © Nortec Electronics 2018
9.3.4 Program 216: Charging lead battery commercial open
16: Lead battery vented commercial
Select Batteryprocessing:
P2: Charge
Enter:
Nominal voltage
Rated capacity
Step 1:
In case battery voltage before charging is below 2.15
V × number of cells:
Precharge with 2.4
V × number of cells until charging current of 0.25
C
1
is reached.
This step is not printed if it takes less than 3 minutes.
Step 2:
I-charge with 0.25
C
1
until the charging voltage of 2.4
V × number of cells is reached.
Step 3:
U-charge with 2.4
V × number of cells until charging current is decreased to 0.04
C
1
.
End of program
Time monitoring:
Precharge maximum 6 hours, I- and U-charge maximum 8 hours, capacity maximum 1.5 × C
9.3.5 Program 217: Charge Pb battery MIL P3-C Orion
17: Pb battery MIL P3-C Orion
select Batteryprocessing:
P2: Charge
Enter:
None, nominal voltage and capacity are preselected by the program
Step 1:
I-charge with C
5
for 5 hours (limit 2.375
V/cell).
Step 2:
I-charge with C
10
for 2.5 hours (limit 2.375
V/cell).
End of program

Table of Contents

Related product manuals