9.4.5 Program 324: Capacity Test NiCd battery MARATHON
Name according to manual: Capacity Check for MARATHON with C
1
24: NiCd battery MARATHON
select Batteryprocessing:
P3: Capacity Test
Enter:
Number of cells
Rated capacity
Step 1:
Discharging with C
1
until a voltage of 1 V for each cell is reached.
In case no automatic cell tester is connected:
After 51 and 60 minutes a signal requests the measurement of the single cells voltages.
Otherwise: Cell measurement is done automatically as soon as a cell is below 1.0 V.
After that discharging with C
1
until a voltage of 1 V for each cell is reached.
WARNING NOTE: „Battery discharged“
End of program
In case an automatic cell tester is connected:
Displayed is the capacity during discharging measured at the moment the first cell is below 1 V.
Example:
Connected is a 24 V battery with 40 Ah. The battery is discharged with 40 A to 20 V.
Time monitoring:
Discharging maximum 90 minutes.