Set-up and Initial Commissioning
21
8.02 Initial commissioning
O Clean the machine thoroughly before the initial commissioning, see also chapter 12
Maintenance and Care.
O Inspect the machine and in particular the electric lines and pneumatic connecting hoses
for possible damage.
O Have technical staff check whether the machine's motor may be operated at the existing
mains voltage.
Do not operate the machine if there are any differences!
The machine must only be connected to a grounded socket!
O Connect the machine to the compressed air system. The manometer should display
a pressure of 6 bar. Adjust this value if required, see chapter 12.03 Checking the
maintenance unit.