Set-up and Initial Commissioning
20
8 Set-up and Initial Commissioning
Check the machine for transport damage after unpacking it. Please notify the carrier and the
relevant PFAFF agency in the event of any damage.
The machine may only be set up and started up by qualified personnel! All of
the relevant safety regulations must always be complied with in this process!
8.01 Set-up
Suitable electrical and compressed air supply connections must be provided at the erection
site, see chapter 3 Technical Data. The erection site must also have a firm and level
subsurface and adequate lighting.
The table top is lowered for packaging purposes.
The adjustment of the table height is described below.
8.01.01 Setting the table height
O Loosen the screws 1 and 2.
O Move the table top to the desired working height by pulling it out and pushing it in and
align the table top horizontally.
Adjust the stand on both sides evenly to prevent it tilting.
O The stand must have all four feet firmly on the ground to make sure it is positioned
securely.
O Firmly tighten the screws 1.
O Adjust and tighten the desired pedal position on the screws 2.
Fig. 8 - 01
1
2
1