Powerware 9330 (10 kVA--40 kVA) Installation and Operation
164201300 Rev . N 013004
1-- 1
n
Getting Started
1.1 Installing the UPS
The cabinet sections of the UPS are shipped on s eparate pallets. Use a forklift or
pallet jack, rated to handle the weight of the cabinets (refer to Drawing
164201300---3 in Appendix A for cabinet weights), to move the packaged cabinet
sections to the installation site, or as close as possible to the site, before unloading
from the pallet.
This is the basic sequence of the installation steps:
1. Create an installation plan for the UPS system (Chapter 1).
2. PrepareyoursitefortheUPSsystem(Chapter1).
3. Inspect, unpack, and unload the UPS cabinet sections (Chapter 1).
4. Wire the system (Chapter 2).
5. Install features, accessories, and/or options, as applicable (Chapter 3).
6. Complete the Installation Checklist (Chapter 2).
7. Have authorized service personnel perform preliminary operational checks and
startup.
NOTE: Startup and operational checks should be performed only by authorized
service personnel. This service is usually offered as part of the sales
contract for your UPS. C ontact service in advance (usually a two week
notice is required) to reserve a preferred startup date.
1.1.1 Creating an Installation Plan
Before beginning to install the UPS system, read and understand how this manual
applies to the system being installed. Use the procedures and illustrations in the
following chapters to create a logical plan for installing the s ystem.
1.1.2 Preparing Your Site
For your UPS system to operate at peak efficiency, your installation site should
meet the environmental parameters outlined in this manual. If you intend to
operate the system at an altitude higher than 1500 meters (5000 feet), contact your
local sales or service office for important information about high altitude operation.
The operating environment must meet the weight, airflow, size and clearance,
requirements specified in Appendix A.
1