Installation
GMS800 · Operating Instructions · 8013025 V1.2 · © SICK MAIHAK GmbH 25
Subject to change without notice
3.3.6 Providing installations for test gases (when required)
When cyclic adjustments are to be setup or when the test gases are to be fed automati-
cally during adjustments:
b
Make the required test gases (
→
p. 43, §6.3) available in pressure cylinders or from
pressure lines.
b
Install suitable pressure reducers to provide the correct feed pressure
(
→
Supplementary Operating Instructions for the Analyzer Modules fitted).
b
Install solenoid valves or similar devices for electric control of the test gas feed.
b
Configure the GMS800 digital outputs to control the solenoid valves (
→
Supplementary
Operating Instructions for “I/O Module”).
b
Connect the solenoid valves to the digital outputs.
b
Assign the test gases to the suitable digital output in the Test Gas Table (
→
Technical
Information for Control Unit).
Fig. 5 Installations for gas feed (example for emission measurement)
7
8
4 6
5
M
M
3
1
2
1 Extraction point
2Dust filter
3 Heated sample gas line
4Gas pump
5 Sample gas cooler
6 Fine dust filter
7Test gases
8 Gas analyzer