START-UP
Fig. 63: Cable connections on the purge air fixtures
Fig. 64: Cable connections on the SR-unit (underside)
▸ Switch on the power supply for the SR-unit and the evaluation unit.
▸ Carry out fine alignment according to
“Fine adjustment on the optical axis on the SR-
unit”, page 79.
▸ Check once again that optical alignment is correct, preferably after having waited
approx. 30 minutes for the system to reach operating temperature.
▸ To do this, call up menu Adjust Probe on the EvU and check the values displayed. See
page 79.
▸ Reactivate Measuring mode:
– Press meas
Regular measuring operation now starts.
CAN cable for SR-unit,
underside
CAN cable, SR-unit –
reflector
Low-pressure monitor
SLV of SR-unit
Low-pressure monitor
SLV of reflector
Temperature sensor
PT 1000
Power supply cable
CAN cable to purge
air fixture
CAN cable to EvU
Functional earth cable
(2.5 mm
2
)